KUALA LUMPUR (July 30): State oil firm Petronas will start up the refinery within its $19 billion petrochemicals complex in Malaysia at end 2017, the company told Reuters on Tuesday, signalling a further delay in the country's largest-ever infrastructure project.
A delay to the project in southern Johor state could deal a potential blow to the economy of the Southeast Asian nation as well as local oil and gas services firms hoping for work on the massive complex.
A source familiar with Petronas's business strategy told Reuters the project had been complicated by a need to secure water supplies as well as cater for proposed international partners.
Petronas had already put back the project from late 2016 to early 2017 in June and revised the final investment decision (FID) to the first quarter next year, citing state government problems in relocating villages and graves from the 2,000 hectare-site, five times the size of New York's Central Park.
"As a result of the revised FID date, the RAPID refinery is scheduled to be ready for start-up in Q4 2017 and the remaining plants within the complex is scheduled to be commissioned in 2018," Petronas said in a statement to Reuters on Tuesday.
This is about six months later than market expectations after local media had cited Petronas CEO Shamsul Azhar Abbas in June as saying the start date for phase one of the RAPID project had been pushed back to early 2017.
BIGGEST INVESTMENT
Delays in the project - a cornerstone of Prime Minister Najib Razak's Economic Transformation Programme aimed at doubling Malaysians' incomes by 2020 - could slow an economy whose oil and gas sector makes up a fifth of GDP.
The complex is the largest single investment in Malaysia, and aims to grab a chunk of the $400 billion global market for speciality chemicals used in products from LCD televisions to diapers.
Its location at the southernmost tip of the peninsula, just 10 km (6 miles) from Singapore's east coast, is part of a vision for a "Greater Singapore" energy trading hub that would rival competitors such as China.
"This massive project is getting more complicated as we move forward," said the source, who declined to be named as he was not authorised to speak to the media.
"We will need to spend to secure the water supply and now parts of the project may need to be redesigned to cater for incoming project partners," he added.
Petronas, Malaysia's only Fortune 500 company, has signed heads of agreements with Italy's Versalis SpA, Japan's Itochu and Bangkok-listed PTT Global Chemical to build speciality chemical plants.
Germany's Evonik also stepped in to the project after rival BASF - the world's top chemicals group - pulled out after differences in business strategy.
Business & Markets 2013
Written by Reuters
Tuesday, 30 July 2013 15:25
KUALA LUMPUR (July 30): State oil firm Petronas will start up the refinery within its $19 billion petrochemicals complex in Malaysia at end 2017, the company told Reuters on Tuesday, signalling a further delay in the country's largest-ever infrastructure project.
A delay to the project in southern Johor state could deal a potential blow to the economy of the Southeast Asian nation as well as local oil and gas services firms hoping for work on the massive complex.
A source familiar with Petronas's business strategy told Reuters the project had been complicated by a need to secure water supplies as well as cater for proposed international partners.
Petronas had already put back the project from late 2016 to early 2017 in June and revised the final investment decision (FID) to the first quarter next year, citing state government problems in relocating villages and graves from the 2,000 hectare-site, five times the size of New York's Central Park.
"As a result of the revised FID date, the RAPID refinery is scheduled to be ready for start-up in Q4 2017 and the remaining plants within the complex is scheduled to be commissioned in 2018," Petronas said in a statement to Reuters on Tuesday.
This is about six months later than market expectations after local media had cited Petronas CEO Shamsul Azhar Abbas in June as saying the start date for phase one of the RAPID project had been pushed back to early 2017.
BIGGEST INVESTMENT
Delays in the project - a cornerstone of Prime Minister Najib Razak's Economic Transformation Programme aimed at doubling Malaysians' incomes by 2020 - could slow an economy whose oil and gas sector makes up a fifth of GDP.
The complex is the largest single investment in Malaysia, and aims to grab a chunk of the $400 billion global market for speciality chemicals used in products from LCD televisions to diapers.
Its location at the southernmost tip of the peninsula, just 10 km (6 miles) from Singapore's east coast, is part of a vision for a "Greater Singapore" energy trading hub that would rival competitors such as China.
"This massive project is getting more complicated as we move forward," said the source, who declined to be named as he was not authorised to speak to the media.
"We will need to spend to secure the water supply and now parts of the project may need to be redesigned to cater for incoming project partners," he added.
Petronas, Malaysia's only Fortune 500 company, has signed heads of agreements with Italy's Versalis SpA, Japan's Itochu and Bangkok-listed PTT Global Chemical to build speciality chemical plants.
Germany's Evonik also stepped in to the project after rival BASF - the world's top chemicals group - pulled out after differences in business strategy.
Cals- Administrator
- Posts : 25277 Credits : 57721 Reputation : 1766
Join date : 2011-09-08
Location : global
Comments : “My plan of trading was sound enough and won oftener that it lost. If I had stuck to it Iâ€d have been right perhaps as often as seven out of ten times.â€
Stock Exposure : Technical Analysis / Fundamental Analysis / Mental Analysis
Similar topics
» Reuters Exclusive Malaysia's Petronas exiting Venezuela crude project
» Petronas refinery in Durban 'running normally'
» Petronas to decide on Johor refinery mid-2013
» Petronas confirms fire at Kerteh refinery
» Amresearch maintains Hold on PChem despite SAMUR project delay
» Petronas refinery in Durban 'running normally'
» Petronas to decide on Johor refinery mid-2013
» Petronas confirms fire at Kerteh refinery
» Amresearch maintains Hold on PChem despite SAMUR project delay
Page 1 of 1
Permissions in this forum:
You cannot reply to topics in this forum
|
|