MAHB seeks damages from tardy klia2 contractors
Business & Markets 2013
Written by Kamarul Anwar of theedgemalaysia.com
Wednesday, 29 May 2013 19:53
A + / A - / Reset
KUALA LUMPUR (May 29): Malaysia Airports Holdings Bhd (MAHB)
has decided to impose liquidated ascertained damages (LAD) on
contractors who caused a delay in the CONSTRUCTION [] of the klia2
Airport, the group said.
MAHB said its board today took note of the contractors’ notification that
they are unable to meet contractual obligations for the opening date of
June 28 this year.
“The board (of MAHB) has decided to impose LAD on the respective
contractors and any other recourse available to MAHB under the
contract. The contractors have requested time to revert with a revised
date,” said MAHB in its filing to Bursa.
Written by Kamarul Anwar of theedgemalaysia.com
Wednesday, 29 May 2013 19:53
A + / A - / Reset
KUALA LUMPUR (May 29): Malaysia Airports Holdings Bhd (MAHB)
has decided to impose liquidated ascertained damages (LAD) on
contractors who caused a delay in the CONSTRUCTION [] of the klia2
Airport, the group said.
MAHB said its board today took note of the contractors’ notification that
they are unable to meet contractual obligations for the opening date of
June 28 this year.
“The board (of MAHB) has decided to impose LAD on the respective
contractors and any other recourse available to MAHB under the
contract. The contractors have requested time to revert with a revised
date,” said MAHB in its filing to Bursa.
hlk- Moderator
- Posts : 19013 Credits : 45112 Reputation : 1120
Join date : 2009-11-14
Location : Malaysia
Similar topics
» Ramunia seeks more jobs from Petronas, other contractors
» Theta Edge seeks RM11.4 mil damages from Tenaga
» RHB says "buy" MAHB despite KLIA2 possible delay as fundamentals promising
» RHB maintains 'buy' on MAHB ahead of klia2 opening
» MAHB falls to low of RM6.05 on worries about delay in klia2
» Theta Edge seeks RM11.4 mil damages from Tenaga
» RHB says "buy" MAHB despite KLIA2 possible delay as fundamentals promising
» RHB maintains 'buy' on MAHB ahead of klia2 opening
» MAHB falls to low of RM6.05 on worries about delay in klia2
Page 1 of 1
Permissions in this forum:
You cannot reply to topics in this forum