Hot Stock Pestech rises to record high on RM1.59b Cambodian concession
Page 1 of 1
Hot Stock Pestech rises to record high on RM1.59b Cambodian concession
Hot Stock
Pestech rises to record high on RM1.59b Cambodian concession
By Chester Tay / theedgemarkets.com | April 9, 2015 : 11:04 AM MYT
KUALA LUMPUR (Apr 9): [size=14]Pestech International Bhd ([You must be registered and logged in to see this image.] Financial Dashboard) saw its share prices rise to a record high of RM5.56 this morning on the group’s RM1.59 billion 25-year Cambodian power transmission concession.
As at 10.50am, the counter retreated to RM5.50, up 14 sen or 2.61% from the previous closing price of RM5.36.
Yesterday, the power system engineering and technical solutions provider announced that its 60%-owned subsidiary Diamond Power Ltd (DPL) has procured all the necessary legal documentation relating to the development of the 230kV Kampong Cham–Kratie transmission system project in Cambodia on a build–operate–transfer basis.
According to Pestech's (fundamental: 0.9; valuation: 0.7) filing with Bursa Malaysia, the duration and validity of the power transmission agreement and novation agreement for the implementation agreement will continue for 25 years from the scheduled commercial operation date.
“The power transmission charges to be paid by Electricite Du Cambodge, Cambodia’s state-owned utility company, to DPL will be US$12.25 million (RM44.51 million) per year for the first three operating years from the scheduled commercial operation date,” the filing read.
The rates will then be US$18.22 million (RM66.2 million) per year from the fourth operating year until the end of the term.
The total collection of charges will amount to US$437.5 million (RM1.59 billion) for the entire 25-year concession period.
The project aims to bring electricity from the upcoming Hydropower Lower Sesan 2 Co Ltd hydropower plant in Stung Treng to Kratie and Kampong Cham.
This signifies the full and effective ownership of the project by DPL, and marks the entry of the Pestech group as an independent power transmitter.
The cost for the development of the project is US$92.21 million (RM335.4 million), which is to be completed by Nov 30, 2017.
(Note: The Edge Research's fundamental score reflects a company’s profitability and balance sheet strength, calculated based on historical numbers. The valuation score determines if a stock is attractively valued or not, also based on historical numbers. A score of 3 suggests strong fundamentals and attractive valuations.)
[/size]
Pestech rises to record high on RM1.59b Cambodian concession
By Chester Tay / theedgemarkets.com | April 9, 2015 : 11:04 AM MYT
KUALA LUMPUR (Apr 9): [size=14]Pestech International Bhd ([You must be registered and logged in to see this image.] Financial Dashboard) saw its share prices rise to a record high of RM5.56 this morning on the group’s RM1.59 billion 25-year Cambodian power transmission concession.
As at 10.50am, the counter retreated to RM5.50, up 14 sen or 2.61% from the previous closing price of RM5.36.
Yesterday, the power system engineering and technical solutions provider announced that its 60%-owned subsidiary Diamond Power Ltd (DPL) has procured all the necessary legal documentation relating to the development of the 230kV Kampong Cham–Kratie transmission system project in Cambodia on a build–operate–transfer basis.
According to Pestech's (fundamental: 0.9; valuation: 0.7) filing with Bursa Malaysia, the duration and validity of the power transmission agreement and novation agreement for the implementation agreement will continue for 25 years from the scheduled commercial operation date.
“The power transmission charges to be paid by Electricite Du Cambodge, Cambodia’s state-owned utility company, to DPL will be US$12.25 million (RM44.51 million) per year for the first three operating years from the scheduled commercial operation date,” the filing read.
The rates will then be US$18.22 million (RM66.2 million) per year from the fourth operating year until the end of the term.
The total collection of charges will amount to US$437.5 million (RM1.59 billion) for the entire 25-year concession period.
The project aims to bring electricity from the upcoming Hydropower Lower Sesan 2 Co Ltd hydropower plant in Stung Treng to Kratie and Kampong Cham.
This signifies the full and effective ownership of the project by DPL, and marks the entry of the Pestech group as an independent power transmitter.
The cost for the development of the project is US$92.21 million (RM335.4 million), which is to be completed by Nov 30, 2017.
(Note: The Edge Research's fundamental score reflects a company’s profitability and balance sheet strength, calculated based on historical numbers. The valuation score determines if a stock is attractively valued or not, also based on historical numbers. A score of 3 suggests strong fundamentals and attractive valuations.)
[/size]
Cals- Administrator
- Posts : 25277 Credits : 57721 Reputation : 1766
Join date : 2011-09-08
Location : global
Comments : “My plan of trading was sound enough and won oftener that it lost. If I had stuck to it Iâ€d have been right perhaps as often as seven out of ten times.â€
Stock Exposure : Technical Analysis / Fundamental Analysis / Mental Analysis
Similar topics
» Stock With Momentum KFM rises 6%, Teo Seng hit record high
» Hot Stock Pestech rises after securing RM318m contract
» Petronas Dagangan rises to record high
» Hot Stock Tenaga at new record high after Edge FD reports stock still has legs
» Pestech to build RM282m Cambodian electricity-transmission line
» Hot Stock Pestech rises after securing RM318m contract
» Petronas Dagangan rises to record high
» Hot Stock Tenaga at new record high after Edge FD reports stock still has legs
» Pestech to build RM282m Cambodian electricity-transmission line
Page 1 of 1
Permissions in this forum:
You cannot reply to topics in this forum