MRT Corp likely to award two viaduct packages
Page 1 of 1
MRT Corp likely to award two viaduct packages
KUALA LUMPUR: Two viaduct packages worth close to RM2bil for the
nation's biggest infrastructure project, Klang Valley My Rapid Transit
(KVMRT), are expected to be awarded tomorrow.
MRT Corp chief executive Datuk Azhar Abdul Hamid told StarBiz that these were two of the last three packages for viaducts construction.
“We
are meeting the Prime Minister this Thursday on the matter and will
soon thereafter announced the awards of Viaducts 2 and 3, which are
quite a big projects as they run along several stations for each
packages,” he said.
He added that these two awards were in the open tender category.
Each of the two viaduct packages is estimated to be worth slightly less than RM1bil.
Viaduct
2, with total length of 5.4km, runs along three stations and Viaduct 3,
with total length of 6.26km, runs along four stations.
In
general, these two packages will involve the construction of elevated
civil works from stations in Kota Damansara to Section 17.
A viaduct guideway is an elevated guideway structure where the tracks for the MRT trains will be located in.
There are eight of these packages five under the open category and the remainder under bumiputra category.
The last viaduct package to be awarded is number eight, which is currently under tendering process.
In
total, MRT Corp has awarded 31 of the total 85 Klang Valley MRT
packages for Line 1 to date, valued at RM13.83bil. The remaining 85
packages for Line 1 would be awarded by December.
Line 1, which connects Sungai Buloh to Kajang via track that runs through the city centre, is made up of two phases.
The first phase is from Sungai Buloh to Semantan, and the second from Kajang to Taman Maluri.
Amir expects the first phase to be operational by December 2016, and the second by June 2017.
nation's biggest infrastructure project, Klang Valley My Rapid Transit
(KVMRT), are expected to be awarded tomorrow.
MRT Corp chief executive Datuk Azhar Abdul Hamid told StarBiz that these were two of the last three packages for viaducts construction.
“We
are meeting the Prime Minister this Thursday on the matter and will
soon thereafter announced the awards of Viaducts 2 and 3, which are
quite a big projects as they run along several stations for each
packages,” he said.
He added that these two awards were in the open tender category.
Each of the two viaduct packages is estimated to be worth slightly less than RM1bil.
Viaduct
2, with total length of 5.4km, runs along three stations and Viaduct 3,
with total length of 6.26km, runs along four stations.
In
general, these two packages will involve the construction of elevated
civil works from stations in Kota Damansara to Section 17.
A viaduct guideway is an elevated guideway structure where the tracks for the MRT trains will be located in.
There are eight of these packages five under the open category and the remainder under bumiputra category.
The last viaduct package to be awarded is number eight, which is currently under tendering process.
In
total, MRT Corp has awarded 31 of the total 85 Klang Valley MRT
packages for Line 1 to date, valued at RM13.83bil. The remaining 85
packages for Line 1 would be awarded by December.
Line 1, which connects Sungai Buloh to Kajang via track that runs through the city centre, is made up of two phases.
The first phase is from Sungai Buloh to Semantan, and the second from Kajang to Taman Maluri.
Amir expects the first phase to be operational by December 2016, and the second by June 2017.
hlk- Moderator
- Posts : 19013 Credits : 45112 Reputation : 1120
Join date : 2009-11-14
Location : Malaysia
Similar topics
» MRT Corp awards 50 work packages
» MRT Corp: 17 packages worth RM7.6b offered to Bumiputeras
» MRT Corp awards four more packages worth RM767mil
» MRT Corp award jobs worth RM3.47b
» AZRB to start work on MRT viaduct this month
» MRT Corp: 17 packages worth RM7.6b offered to Bumiputeras
» MRT Corp awards four more packages worth RM767mil
» MRT Corp award jobs worth RM3.47b
» AZRB to start work on MRT viaduct this month
Page 1 of 1
Permissions in this forum:
You cannot reply to topics in this forum